This template models a programme with an upgrade or confirmation review, two studies and a viva. It runs for about 38 months: submission is around month 34, followed by examination and corrections. Your programme's stages and deadlines may differ.
For a single study or a dissertation lasting less than a year, start with the research project plan. It covers one research project rather than the programme around it.
In this sample, year one covers the proposal, ethics and upgrade review. Research and writing overlap in years two and three, with a separate period after submission for the viva and corrections.
| Phase | Months | What happens |
|---|---|---|
| Progress reviews | 6, 12, 24, 30 | The six-month review, the upgrade report and the upgrade or confirmation milestone at month 12, then annual reviews in years two and three. |
| Literature review and proposal | 1 to 9 | Scope agreed with the supervisors, a systematic search, sixteen weeks of reading, the review chapter drafted and the proposal written alongside it. Ends on Proposal agreed. |
| Ethics and preparation | 9 to 13 | The ethics application, the committee wait with the instruments built during it, approval, a pilot and the revised protocol. |
| Fieldwork or experiments | 13 to 26 | Study 1 recruited, collected and analysed, then Study 2 designed from what Study 1 found, collected and analysed, and the findings brought together. |
| Writing the thesis | 15 to 33 | Methods while Study 1 runs, each results chapter after its analysis, the discussion, the literature review updated, the introduction last, then the full draft, the supervisors' wait and the revisions. |
| Submission and viva | 34 to 38 | Formatting and the final proofread, submission at about month 34, the examiners' wait, viva preparation, the viva, corrections and the final deposit. |
Choose Use template to create a copy starting on the coming Monday. Before using its dates, work through these changes with your supervisor:
Study 1 recruitment in the sample waits for both the revised pilot protocol and the upgrade milestone. That makes a delayed approval visible in the research schedule. Remove or change this dependency if your programme permits work to begin earlier.
The sample places the pilot before the upgrade review, assuming the necessary ethics approval is already in place. Check that assumption before copying the sequence.
The other progress reviews have no outgoing dependencies in this plan. If one is an approval gate in your programme, link it to the work that must wait.
Three Wait bars separate turnaround time from your own research effort:
Turn on Critical path to inspect the chain controlling the finish date. With Auto schedule on, extend a wait and review its effect on submission and the final deposit.
The sample starts the methods chapter during Study 1, around month 15. Draft what is known and revise it as the research develops. Each results chapter follows its analysis, while the discussion follows the combined findings.
A separate literature-update task brings the early review up to date before the full draft. The plan also reserves time for supervisor feedback, revisions and a final proofread.
Submission around month 34 leaves some room before the end of a three-year period. Treat that as a sample buffer, then check it against your actual registration and funding deadlines.
The preview opens at Year zoom for the full programme. Use Quarter zoom for a review meeting and Month zoom for upcoming work. Fit view chooses a scale that shows the whole plan.
Keep chapters, studies and approval stages as the main rows. Collapse groups for a programme overview, then export a PDF for the review pack or an image for a progress report.