High-level vs detailed Gantt charts: how much detail?
A high-level Gantt chart shows a project as a handful of phase bars and its key milestones, with no individual tasks. A detailed Gantt chart shows every task with its dates, its owner and what it waits for. Choose the high-level view for sponsors and clients, and the detailed view for people doing the work. The number of rows depends on the reader and how often dates change.
Most projects need both, drawn from the same plan. The sample website project below has three levels: a summary, a working schedule and a detailed view of the next few weeks. Five tests help decide which bars to split.
How do high-level and detailed Gantt charts differ?
The difference is the question each chart answers. A high-level chart answers "when does each stage finish, and are we on track for the end date?" A detailed chart answers "what does each person do this week, and what are they waiting for?" One is read in a meeting once a month; the other is read every morning.
| High-level | Working schedule | Detailed | |
|---|---|---|---|
| Rows show | Phases and milestones | Tasks with owners and links | Short pieces of work for the next few weeks |
| Read by | Sponsor, client, board | Project lead, team leads | The people doing the work |
| Time scale | Weeks or months | Days or weeks | Days |
| Changes | Rarely; a change here is news | At every weekly review | Whenever something slips |
The working schedule is the version the project lead keeps up to date. The high-level chart is a summary of it, and the detailed chart is a close-up of its next stretch.
Level 1: what belongs on a high-level Gantt chart?
A high-level Gantt chart of the sample project has four phase bars and two milestones. It fits on half a page and takes ten seconds to read.
The sample is a website redesign that runs from 1 September to 21 October, ten tasks in all. The dates are sample data.
| Row | Start | Finish |
|---|---|---|
| Discovery | 1 Sep | 9 Sep |
| Design and copy | 3 Sep | 28 Sep |
| Milestone: design signed off | 28 Sep | 28 Sep |
| Build | 29 Sep | 19 Oct |
| Test and launch | 15 Oct | 21 Oct |
| Milestone: launch | 21 Oct | 21 Oct |
Three things make this version work. Each phase ends at something a reader cares about, a sign-off or the launch. The overlaps are visible, so nobody is surprised that design starts before discovery ends, or that testing starts while the build is still running. And there are no arrows between phases: at this level an arrow from Design to Build says less than the milestone between them, which shows who decides and when.
Use it for a kickoff, a monthly update or a client proposal. For sending it outside the team, see presenting a timeline to clients.
Level 2: what belongs in the working schedule?
The working schedule is the plan the project lead maintains: every task that has its own dates, owner or dependency. For the sample project that is ten tasks, grouped under the four phases.
| Phase | Task | Start | Working days |
|---|---|---|---|
| Discovery | Kickoff and goals | 1 Sep | 1 |
| Discovery | Content audit | 3 Sep | 5 |
| Design and copy | Wireframes | 3 Sep | 6 |
| Design and copy | Write new copy | 9 Sep | 9 |
| Design and copy | Visual design | 10 Sep | 10 |
| Design and copy | Copy review | 22 Sep | 2 |
| Design and copy | Design sign-off | 24 Sep | 3 |
| Build | Build | 29 Sep | 15 |
| Test and launch | Testing | 15 Oct | 5 |
| Test and launch | Launch | 21 Oct | 1 |
This is the level where dependencies belong. Copy review waits for the new copy; design sign-off waits for the visual design; build waits for the sign-off. When the visual design runs three days long, the working schedule is where you see that the sign-off, the build and the launch all move with it.
Notice what is not here. "Write new copy" is nine days for one writer and nobody waits for half of it, so it stays one bar, with the page list as a checklist. The rules for that call are further down.
Level 3: how detailed should the next few weeks be?
The detailed chart breaks the next stretch of work into pieces of one to five days. In the sample, during the last week of September, that means the build and the testing, the work about to start. The earlier tasks stay as they were.
| Working task | Detailed tasks | Dates |
|---|---|---|
| Build (15 days) | Set up the CMS and hosting | 29 to 30 Sep |
| Build | Build the page templates | 1 to 7 Oct |
| Build | Move the content into the templates | 8 to 13 Oct |
| Build | Forms and analytics | 14 to 15 Oct |
| Build | Fix issues from testing | 16 to 19 Oct |
| Testing (5 days) | Browser and phone checks | 15 to 16 Oct |
| Testing | Proofread every page | 15 to 16 Oct |
| Testing | Retest the fixes | 19 to 20 Oct |
| Testing | Client acceptance | 21 Oct |
Splitting these bars exposes two handoffs. "Move the content" waits for the templates, not for the whole build, and "Fix issues from testing" waits for the first round of checks. Neither of those links can be drawn while Build is one fifteen-day bar.
The detailed chart now has seventeen rows instead of ten. Split every task this way from the first day and the chart would have roughly three times as many rows, most of them guesses. Detailing only the next few weeks is the idea behind planning the next stretch, and it keeps the detail honest.
When should you split a task bar?
Split a bar when the chart would show something it cannot show while the bar is whole. Keep it whole when the pieces would only repeat the same owner and the same dates. Use these five tests:
- Different owners? If two people or two teams do parts of it, split it, so each person sees their own dates.
- Something waits for part of it? If another task can start once a piece is done, split at that point, so the link has somewhere to attach.
- Longer than your update cycle? If you review the plan weekly, a six-week bar is "in progress" at five reviews in a row and tells you nothing. Split it so a piece finishes between reviews.
- A decision inside it? If an approval, a handover or a payment sits in the middle, split there and make it a milestone.
- Just a checklist? If the parts have one owner, nobody waits for them and they finish within one review, keep one bar and list the parts inside the task.
The third test is the one schedulers on large projects lean on. In a discussion among Microsoft Project users about how detailed the baseline for a project of more than $50 million should be, one scheduler's rule was no activity longer than one update period, and one owner per activity. Answers in the same thread ranged from about 150 activities to 3,000, which shows how far apart reasonable people land when they skip the question of who reads the chart.
For working out where the pieces come from in the first place, see breaking work into bars. For how long each piece takes, see setting task durations.
How do you keep three levels in one plan?
Keep one plan and change what you show, instead of drawing three charts. Three separate files drift apart within a fortnight: someone moves the launch in the detailed chart and the client summary still shows the old date.
Most Gantt tools have some way to fold tasks under a phase. Use it like this:
- High-level view: Collapse every phase to its summary bar and keep the milestones visible. Switch the time scale to weeks or months.
- Working view: Expand everything, at a day or week scale. This is the version you edit.
- Detailed view: Expand only the current phase and filter or scroll to the next few weeks.
In Ganttile, for example, a project's lists act as phases: with Show list dates on, each list draws one bar spanning its tasks, and collapsing the lists turns the working schedule into the summary. The PDF and image exports draw only the rows on screen, so the collapsed version prints as the high-level chart.
If your tool has no summary rows, keep the high-level chart as a separate small chart, but update it from the working schedule at every review rather than on its own. A database timeline such as Notion's timeline view can do this with parent items that collapse.
What goes wrong at each level?
A high-level chart can hide risks, a working schedule can fill with checklist items, and a detailed chart can make distant work look certain. Match each view to the decisions its reader needs to make.
- High-level hides the risk. A summary of four phases can hide a two-day task that sets the launch date, such as a domain transfer or a legal review. If one small item could move the end date, show it at the top level, even if it looks out of place.
- Working schedule turns into a to-do list. Once every checklist item has a bar, nobody updates it, and a chart nobody updates is worse than none. Push the small stuff back inside the tasks.
- Detailed chart reaches too far. Day-level tasks for work three months away are guesses with dates on them. They make the plan look certain when it is not.
- Levels are mixed on one page. A phase bar next to a two-hour task reads as if both were the same kind of thing. Pick one level per view.
For more problems that make a chart hard to keep, see schedule mistakes to avoid.
High-level and detailed chart questions
- What is a high-level Gantt chart?
- A high-level Gantt chart shows a project's phases and key milestones as a few bars, without individual tasks. It is for people who need the stage dates and the end date rather than the day-to-day work, such as a sponsor or a client.
- How many tasks should a Gantt chart have?
- As many as the reader needs, and no more. A high-level chart may have under ten rows; a working schedule has a row for every piece of work with its own owner, dates or dependency. Split a bar when part of it has a different owner, something waits for part of it, or it runs longer than your review cycle.
- Should a high-level Gantt chart show dependencies?
- Usually not as arrows between phases. A milestone between two phases, such as a sign-off, says more about why the second waits. Keep task-to-task dependencies in the working schedule, where a delay can move the dates after it.
Which level should you draw first?
Draw the working schedule first, because the other two come from it. Add a row for every piece of work with its own owner, dates or dependency, then collapse it to phases and milestones for the high-level view, and expand the next few weeks for the detailed one. When someone asks for "the plan", ask who will read it before you decide how many rows it gets.