Can you make a Gantt chart in Notion?

You can make a Gantt chart in Notion using Timeline view, available on every plan including Free. It draws database items as bars between their dates, with dependencies that can move later items when an earlier one slips. Notion's help does not describe a critical path, a milestone type or an export of the timeline drawing.

A Free workspace with two or more people can add 1,000 blocks in total, and task pages use that allowance. Choose Notion for a simple schedule kept beside the team's notes. Use a separate chart when you need critical path analysis or a plan to send as an image.

Disclosure: Ganttile publishes this comparison and makes one of the free Gantt chart tools discussed below.

A notes page with a small table leads to a timeline of bars where one dependency arrow stops at a question mark

What does Notion Timeline view show?

Timeline view shows the items of a Notion database as bars along a time axis, from the item's start date to its end date. It is a view of a database, not a separate chart, so the same tasks can also appear as a table or a board.

According to Notion's Timeline help, the view gives you:

  • Bars from a date range. The database needs at least one date property holding a range, or two properties for start and end. Without one, nothing is plotted.
  • Any time scale. From hours up to years, picked from a dropdown beside the Today button.
  • Drag to reschedule. Pull either end of a bar to change its length, or drag rows up and down to reorder them.
  • A table beside the bars. Shown or hidden with the arrows on the left, with whichever properties you choose and column calculations such as a sum of hours.
  • Sub-items. A parent item can hold sub-items that open and close under it in a toggle.

Each Notion bar is a full page that can hold the brief, files and discussion for that task. A Gantt chart tool holds a name and dates. Which matters more depends on whether the timeline is where people do the work or where somebody plans it.

Does Notion Timeline have dependencies?

Yes. Dependencies are available on every plan, Free included, and once they are on, an arrow joins a task to the task it blocks. Notion can also move the blocked task when the earlier one moves, so linked work can follow a changed date.

Notion's help on sub-items and dependencies puts the switch in the database settings, under More settings, then Dependencies. Turning it on creates a relation property that links items in the same database. Then you hover over a bar in the timeline and drag its arrow onto the task it blocks.

The choice that matters is how dates move. Notion offers three options:

Option What happens when a blocking task slips Use it when
Shift only when dates overlapThe blocked task moves only once the two would overlap, so any gap between them shrinks firstYou left slack between tasks on purpose
Shift and maintain time between itemsThe blocked task moves by the same amount, keeping the gapThe gap is real waiting time, such as a review or a delivery
Do not automatically shiftNothing moves; the arrow is only a reminderDates are fixed by someone else and you only need to see the order

A separate toggle stops shifted items from starting or ending on a weekend. Turn it on: without it, a two-day slip on a Thursday task can push the next one onto a Saturday.

Notion describes dependencies as connecting tasks "in a linear way", one task blocking the next, and its help mentions no other link type: no start-to-start, no finish-to-finish, no lag. And the arrows appear only in the timeline. In the table or board view the link is a relation property listing task names.

What are Notion Timeline's Gantt chart limits?

Notion Timeline supports bars, dates and blocking links. Its help does not describe critical path analysis, a milestone type or additional dependency types, and it does not establish whether PDF exports include timeline bars.

Gantt chart feature In Notion Timeline Workaround
Critical pathNot described in Notion's helpTrace the longest chain of linked tasks by hand
MilestonesNo milestone typeA one-day item plus a checkbox property called Milestone, so you can filter for them
Link types and lagBlocking links onlyLeave a gap and use "maintain time between items"
Printable chartPDF export exists; the help does not say it draws the barsTest the export on your own database before promising one

For exports, Notion's export help lets you save a database as a PDF, choosing between the current view and the default view, and says a full-page database cannot be printed straight from the browser. It never says what a timeline looks like in that PDF. If the plan has to go into a client deck or a board paper, try the export early rather than the night before.

Critical path analysis matters when several chains of work affect the finish date. On a timeline with thirty linked tasks, you can see which items are late, but not which delays move the end date and which use up spare time. If that question comes up weekly, it is worth a tool that answers it. See how critical path calculations identify the tasks that set the finish date.

Gantt chart of three parallel tracks converging on an assembly task, labelled with phase, predecessor, successor, finish-to-start, critical path, total float, free float and milestone

How does Notion's block limit affect a project?

The Free plan limits blocks across the workspace, so task pages share the allowance with notes and other content. Notion's block usage help sets it by workspace size: up to 5,000 blocks for a workspace with one person, and 1,000 blocks for a workspace with two or more. Paid plans have no block limit.

A block is any single piece of content, such as a paragraph, a to-do or an image, and every task in a database is a page with content of its own. Notion does not publish a per-row figure, so take the arithmetic below as an estimate:

  • One task: The page itself, a three-line description and four checklist items comes to roughly 8 blocks.
  • One project: Forty such tasks is about 320 blocks, before any meeting notes or files.
  • Two people: Three projects like that use nearly the whole 1,000-block allowance.

The allowance counts content created, not just content you keep. Notion counts every block created since the workspace started, so deleting old tasks or emptying the trash does not lower the count. Content added through the API or connected tools counts too. And on Free, anyone added to the workspace joins as a workspace owner, which is what moves a workspace from the 5,000 limit to the 1,000 one.

At the limit, Notion gives a three-day grace period. After it, you can still view, edit, move, export and delete what is there, but you cannot add new blocks. Settings, then Upgrade plan, shows how many you have used. Plus removes the limit at $10 per seat per month billed yearly, or $12 billed monthly, so a five-person team pays $600 a year.

How do you set up a Gantt chart in Notion?

Use one database for the project's tasks, parent items for phases and dependencies for order. Each task then has dates, a place in the project and links to the work it blocks.

  1. Create the database. Add a Date property that holds a start and an end date, a Milestone checkbox and an Owner property.
  2. Add the Timeline view. Click the plus next to the view name and choose Timeline. If you use two date properties, pick them under Layout, then Show timeline by.
  3. Make phases parent items. Turn on sub-items in the database settings, add one parent item per phase and put the tasks under it. Choose "Nested in toggle" so a phase can collapse to one row.
  4. Turn on dependencies. Pick "Shift and maintain time between items" and switch on the weekend toggle. Then drag the arrows from each task to the one it blocks.
  5. Mark the decisions. Sign-offs and approvals become one-day items with Milestone ticked, so a filtered view lists them all.
  6. Show the table. Open the table beside the bars and show Owner and Date, so the timeline reads like a task list with bars.

Keep the task pages short if you are on Free. A long description inside every task is where the blocks go. A shared brief page linked from the database costs far fewer than forty copies of the same notes. To decide how many rows the timeline needs at all, see choosing the chart's detail.

When should you move the schedule out of Notion?

Keep the work in Notion and put the dates and links in a separate Gantt chart. This suits a project where one person owns the schedule, the team needs a critical path, or the plan has to be sent outside the workspace as a picture.

Start by exporting the task database. Notion exports a full-page database as a CSV file from the Export menu, with Markdown & CSV as the format; Breeze has a walkthrough for exporting your Notion data. Open the CSV in a spreadsheet and keep only the rows that have dates. Ideas, notes and recurring chores stay in Notion.

In Ganttile, a free online Gantt chart maker, a project holds lists and each list holds tasks. Rename the starting lists to your phases, add the tasks with their start and end dates, and drag from the end of one bar to the start of the next to link them. Ganttile accepts finish-to-start, start-to-start, finish-to-finish and start-to-finish links. A milestone is a one-day task with its own colour.

In the chart settings, Hide weekends counts working days, Show list dates draws one bar per phase, and Critical path and Auto schedule are off until you turn them on.

Ganttile does not import a Notion CSV, so enter the task names by hand. A task holds a name, dates, its list and a colour, not the page content a Notion item carries. For a project of a few dozen tasks, this is a short job, and the chart costs no blocks.

Export the chart as PDF, PNG, Excel or Microsoft Project XML, or send a read-only link to anyone outside the team. Inviting teammates to edit needs Ganttile Pro, at $10 per user per month.

For tasks and a timeline in one tool, Breeze imports from Notion and has a Gantt view. It costs $9 per user per month billed yearly, or $10 billed monthly, with every feature included.

A Ganttile chart of a sample website redesign with three phases as lists, linked tasks and two milestones, design approved and launch

Choose where to maintain the dates. If Notion keeps a date field too, the two schedules will drift within weeks. Keep the dates in the chart and put a link to it at the top of the Notion project page. The guide to linking dependent tasks covers which links to draw first.

When should the timeline stay in Notion?

Keep it in Notion when the team already works there and the schedule is simple. A content calendar, a hiring pipeline or a launch with a handful of linked tasks fits Timeline well, and having the brief inside each bar saves a trip to another tool.

Notion also makes sense when you pay for Plus anyway, so blocks are not a worry, and when nobody outside the workspace needs a printed plan. The dependency shifting covers the common case of "if this slips, move the next thing".

Move the schedule out when any of these is true: the project has more than one chain of linked work and you need to know which chain sets the end date; a client or a board wants the plan as a PDF or an image; or a Free workspace with several people is already close to its 1,000 blocks.

Notion Gantt chart questions

Does Notion have a Gantt chart?
Notion calls it Timeline view. It shows database items as bars between their dates and can link them with dependencies that shift later items. Notion's help does not describe a critical path or a milestone type.
Is Notion's Timeline view free?
Yes. Notion's pricing page lists databases with sub-items and dependencies on the Free plan. The limit is blocks: a Free workspace can add 5,000 blocks with one person, or 1,000 with two or more.
Can Notion move dependent tasks automatically?
Yes. When you turn on Notion dependencies, you choose to shift blocked tasks only when dates overlap, to shift them and keep the gap, or not to shift them. A separate toggle keeps shifted tasks off weekends.

Which setup fits your project?

For a short plan with a few links, use Timeline with dependencies set to keep the gap, and phases as parent items. For a project where the end date depends on several chains of work, or one that must be printed, keep the tasks in Notion and the schedule in a Gantt chart. On a Free workspace shared by several people, count your blocks before you build forty task pages.

Export the tasks that have dates, turn them into phases and links, and mark the decisions. Create your free chart to give the plan a critical path.