Horizon Europe project Gantt chart template

This Horizon Europe Gantt chart template contains a sample 36-month consortium work plan, grouped into work packages with deliverables and milestones labelled by project month. Edit and export it for Part B section 3.1.

A Horizon Europe project Gantt chart in Ganttile by quarter, with work packages as groups, numbered tasks, dependency arrows and the first deliverables and milestones
  • 5 work packages
  • 41 tasks
  • 5 milestones and 12 deliverables
  • 43 dependencies
  • 36 months

The project, partners and durations are sample data. The structure follows the standard application form for Research and Innovation Actions and Innovation Actions.

What does Part B section 3.1 ask for?

Section 3.1, Work plan and resources, asks for the timing of the work packages and their components as a Gantt chart or similar, a Pert chart or similar, and tables of work packages, deliverables and milestones.

Two rules shape the chart. Sections 1 to 3 share a 40-page limit (45 for lump sum topics), figures included. Deliverable and milestone dates count months from month 1, not calendar dates.

How is the work package Gantt chart laid out?

Each work package groups numbered tasks, T1.1, T1.2 and so on, as in table 3.1b. The sample consortium builds a climate risk tool: its partners are a university, a research institute, a software company and a city network.

Work packageMonthsWhat happens
WP1 Project management1 to 36Kick-off, handbook, data management plan, coordination and general assemblies.
WP2 Requirements and co-design1 to 9Stakeholder mapping, co-design workshops, requirements.
WP3 Model and tool development5 to 33Risk model, prototype, final release, open dataset.
WP4 Pilots and validation15 to 35Two pilot rounds in three cities, each evaluated.
WP5 Dissemination, exploitation and communication1 to 36Plan, website, papers, exploitation plan, final conference.

The form advises a separate project management work package and visible work on data management, dissemination and exploitation, and communication. Partner short names begin each task, so the lead shows in print.

Where do deliverables and milestones go?

Deliverables and milestones appear as markers labelled with their number and project month, matching tables 3.1c and 3.1d. Deliverables use the form's numbering: D4.2 is the second deliverable of WP4.

  • First six months: The form requires a data management plan and a dissemination and exploitation plan as deliverables by then. Here they are D1.2 and D5.1, at M6.
  • Milestones: Requirements agreed (M9), prototype ready for the pilots (M18), pilot round 1 complete (M24), final tool released (M30) and final results presented (M36).

MS1 to MS4 each gate later work: pilot round 1 waits for MS2, round 2 for MS4, and MS5 closes the project. Turn on Auto schedule under Settings and stretch the prototype bar to see everything linked after it move.

How do you export the Horizon Europe work plan for Part B?

Export a PDF and place it as a figure in section 3.1. The export defaults to A4 landscape, fitted to the page width; set a date range to show one year per figure.

The 11-point minimum covers body text and tables; other text must still be legible, so check the smallest label at print size. Keep the tables in plain text, as the form asks. The Excel export gives names, dates and durations to copy from.

  1. Partners: Replace Coordinator, P2, P3 and P4 with your consortium's short names.
  2. Months: The chart uses dates. Update the month label by hand when you move a deliverable.
  3. Share: Send partners a free read-only link, or invite them to edit with Ganttile Pro.

For one institution, choose a three-year research grant schedule; for under a year, a shorter study plan. Splitting work into bars helps break work packages into tasks.

Common questions

Does Horizon Europe require a Gantt chart?

Section 3.1 of the standard application form for Research and Innovation Actions and Innovation Actions asks for the timing of the work packages and their components as a Gantt chart or similar. The form does not set a format or a tool.

Does the Gantt chart count toward the page limit?

Yes. Every table and figure in sections 1 to 3 counts against the Part B limit of 40 pages, or 45 for topics using lump sum funding.

Can I adapt this template for a 24-month project?

Yes. Shorten work packages WP3 and WP4 first, usually by cutting the second pilot round. Move the milestones and update their labels. Keep deliverables D1.2 and D5.1 within the first six months.