The export contains the tasks and dates from an annual report plan. It does not include Gantt bars or dependency arrows. You can add bars in Sheets with conditional formatting after importing the table.
Each task becomes a row, with bold phase rows above their tasks and a frozen header. The sample has these columns:
| Column | What it holds |
|---|---|
| Task name | Each task with its owner at the front, under the bold row for its phase. |
| Start | A date cell, so sorting, filtering and date formulas work on it. |
| Days | How long the bar is, as a number. In your own copy the column is called Duration. |
| End time, when enabled | The task end date. Turn this column on in your own copy before exporting if you want to build Gantt bars in Sheets. |
| Estimate | The hours of work in the task, which is a different thing from the length of the bar. |
To add bars, put week or day columns to the right of the table and colour cells whose dates fall between each task's start and end. The Google Sheets conditional formatting guide explains the setup.
Dependency arrows do not transfer. For example, the export does not preserve the link that makes printing wait for the approved proof. You would need to maintain that relationship yourself in Sheets.
The sample gives a small organisation about fourteen weeks to gather content, write and design an annual report, obtain approvals and publish it. Its timings are starting points to replace with your team's availability and supplier deadlines.
| Phase | Weeks | What happens |
|---|---|---|
| Plan and gather | 1 to 4 | The brief, then the figures, the stories and the photos collected side by side. Ends on All content in. |
| Writing | 4 to 6 | The narrative drafted as soon as the figures and stories arrive, the foreword, then one edit that checks every number. Ends on Copy locked. |
| Design | 3 to 11 | The page template early, the layout once the copy is locked and the photos are in, a proofread and the corrections. |
| Approvals | 4 to 11 | The auditor signing off the figures, drawn as a wait, and the board reading the proof. |
| Print and publish | 5 to 14 | The printer booked early, printing as a wait, the web version, the copies posted. Ends on Annual report published. |
Roles such as Comms, Finance and Designer appear at the start of task names, so they remain visible in the exported table. Replace them with the people doing the work.
You can also adapt the structure for a prospectus, grant report or catalogue. Keep only the approvals and external waits that apply.
The sample allows a month for the auditor and two weeks for printing. Both appear as Wait bars without effort estimates: elapsed time is different from hours of your team's work.
Layout depends on the locked copy, collected content and page template. Board approval depends on the proofread and audit, and printing depends on the approved proof. These are the sample's assumptions; change the links if your approval process differs.
To explore a delay, turn on Auto schedule in your copy and extend the auditor's wait. Review which linked dates move and whether the new publication date is acceptable.
The export goes one way. Ganttile exports an .xlsx but does not import spreadsheets, so edits in Sheets do not return to the chart.
Agree which copy is current if you share both. For colleagues using Excel, the Excel Gantt chart template explains the same export with an office-move example.