Use this plan to coordinate the manager, buddy, HR and IT for one new hire. The sample starts two weeks before day one and covers roughly fifteen weeks in total. Copy it for each person and adjust the dates, responsibilities and review process to their role.
The preparation rows cover equipment, access and a first-week plan, so owners can check readiness before the agreed start date.
Checkpoints sit at the top, followed by preparation, the first week and three stages of learning, taking ownership and delivering work. The timings below describe the sample.
| Group | When | What happens | Owners |
|---|---|---|---|
| Checkpoints | Review dates | A check-in at the end of week one, reviews at 30, 60 and 90 days, and the probation decision. Each review links to the work or feedback to discuss. | Manager |
| Before day one | Two weeks out | Contract and payroll forms, the laptop ordered and its delivery drawn as a wait, accounts set up, a buddy chosen and briefed, the first-week plan written and sent. Ends on Day one. | HR, IT, manager |
| Week one | Day by day | Monday: welcome, kit and logins. Tuesday and Wednesday: intro meetings and the tools walkthrough. Wednesday to Thursday: a first small task. Thursday and Friday: shadowing the buddy on real work. | Manager, buddy, new hire |
| Days 1 to 30: learn | Weeks 2 to 5 | Reading, product and process training, meeting the people they will work with most, and a first real piece of work reviewed by the buddy. The weekly one-to-one starts here and runs to the end. | Buddy, new hire |
| Days 30 to 60: own | Weeks 6 to 9 | A project owned end to end, chosen at the 30-day review, plus joining the rota for their area. The manager collects feedback from the buddy and two peers before the 60-day review. | New hire, manager |
| Days 60 to 90: deliver | Weeks 10 to 13 | The buddy steps back, the project is delivered and presented to the team, HR prepares the probation paperwork. Ends with the probation decision. | New hire, buddy, HR |
The sample allows time to order a laptop, wait for delivery and set up accounts. Kit and accounts ready is linked to Day one so a delay is visible in the schedule.
Do not use a moved chart milestone as a new employment start date. If equipment will arrive late, keep the agreed start date and arrange a workable first day, such as temporary equipment or activities that do not require it.
Confirm the buddy, send the first-week schedule and let the new hire know who to contact. These tasks need named owners as well as dates.
Move the sample checkpoints to your actual review dates. Keep regular check-ins even if a task is delayed; unfinished work may be something the review needs to address.
The sample introduces an owned project after the 30-day review. An experienced hire may be ready sooner, while another role may need more training. Agree responsibility from what the person can do and the support available.
Plan how the buddy's support will change, and keep a regular manager one-to-one throughout the period. The long one-to-one bar represents recurring meetings; schedule the individual meetings in your calendar.
Use Month zoom for the full onboarding period and Week zoom for the first week. Compare effort estimates with each owner's other work rather than assuming short tasks will fit automatically.
For the hiring work before onboarding, the monthly Gantt chart template includes a workstream from the job advertisement through the offer and notice period.